Create Your First Project
Start adding your projects to your portfolio. Click on "Manage Projects" to get started
Seqwater Renewal of Bulk Water Flow
Location
Mount Crosby, Queensland
Client
GHD
Asset Owner
Seqwater
Value
$8.5 million
Independent pre-tender cost and delivery validation for flow meter and pipeline upgrades within a live bulk water network.
Overview - Infravisory supported the renewal of critical bulk water infrastructure, including replacement of electromagnetic and ultrasonic flow meters and a section of large-diameter pipeline, along with associated structural, mechanical, and electrical upgrades. Works were staged within a seven-day window to maintain continuous water supply to Ipswich and Brisbane.
Challenge - The project required validation under strict operational constraints, including working on a live high-priority pipeline, achieving delivery within a tight shutdown window, managing constructability and access challenges, and identifying critical long-lead procurement items.
Infravisory Role - Engaged by GHD, Infravisory delivered a Class 1 P80 pre-tender estimate, including BOQ, construction program, constructability and risk review, and market pricing validation.
Outcome - Infravisory delivered an accurate, market-tested estimate, validated constructability within the seven-day delivery window, identified key procurement risks, and provided confidence in cost, schedule, and delivery prior to tender.